- Visual internal/external test: Performed from the outside of a pressure vessel to find conditions that could impact the vessel’s ability to maintain pressure integrity or conditions that compromise the integrity of the supporting structures
- Hydrostatic testing: The Hydro test is a type of pressure test performed on piping and pressure vessels to check system integrity under pressure condition. A hydrostatic test is performed by using water as the test medium.
- Pneumatic testing: Type of pressure test for checking system integrity under the pressurized condition and applied to systems where the hydro-static test is difficult to apply.
-
Upper Coupler Testing:
Upper coupler assembly. A structure consisting of an upper coupler plate, king-pin and supporting framework which interfaces with and couples to a fifth wheel.
Upper coupler plate. A plate structure through which the king-pin neck and collar extend. The bottom surface of the plate contacts the fifth wheel when coupled.
-
V – External Visual Inspection – Annual Test
-
K – Leakage Test – Annual Inspection
-
I – Internal Visual Inspection – Five Year Test
-
P – Pressure Test – Five Year Test
-
T – Thickness Test – Two Year Test
-
UC – Upper Coupler Inspection – Five Year Test

COMPLIANCE DATES – INSPECTIONS AND TEST UNDER § 180.407©
Test or inspection (cargo tank specification, configuration, and service) |
Date by which first test must be completed (see note 1) |
Interval period after first test |
External Visual Inspection:
|
September 1, 1991
September 1, 1991 |
6 Months
1 Year |
Internal Visual Inspection:
|
September 1, 1991
September 1, 1991 September 1, 1995 |
1 Year
1 Year 5 Years |
Lining Inspection:
|
September 1, 1991 |
1 Year |
Leakage Test:
|
September 1, 1991 September 1, 1991 |
2 Years 1 Year |
Pressure Test: (Hydrostatic or pneumatic) (See Notes 2 and 3)
|
September 1, 1991
September 1, 1992
September 1, 1992 September 1, 1995 |
1 Year
2 Years
2 Years 5 Years |
Thickness Test:
|
September 1, 1992
|
2 Years |

- If a cargo tank is subject to an applicable inspection or test requirement under the regulations in effect on December 30, 1990, and the due date (as specified by a requirement in effect on December 30, 1990) for completing the required inspection or test occurs before the compliance date listed in table I, the earlier date applies.
- Pressure testing is not required for MC 330 and MC 331 cargo tanks in dedicated sodium metal service.
- Pressure testing is not required for uninsulated lined cargo tanks, with a design pressure or MAWP 15 psig or less, which receive an external visual inspection and lining inspection at least once each year.
- Insulated cargo tanks equipped with manholes or inspection openings may perform either an internal visual inspection in conjunction with the external visual inspection or a hydrostatic or pneumatic pressure-test of the cargo tank.
- All phases of truck, trailer, bus, and diesel truck auxiliary power units (A.P.U.) repaired
- Brake service, electrical & air systems repaired, welding & fabricating
- PM services, Fleet service
- Federal DOT inspections
- Hendrickson suspension service
- Tires, new, used & repaired
- A/C service
- Inspection - axles, spindles, king pins, hubs
- Steering axles Replaced – trucks & forklifts
- Drive axles replaced to straightened & repaired - cracks repaired, spring.
- Lengthen & Shorten Frames
- We straighten front axles, drive axles, trailer axles, axles and housings and reattach air beams. Forklift masts & forks straightened